The kickoff meeting is going well. The plan is on the screen, the budget is approved, and the sponsor asks whether anyone has concerns. Nobody does. Six weeks later, three team members each mention the integration problem they spotted on day one.
This is not a story about bad people. It is a story about what planning meetings reward: confidence, momentum and agreement. Gary Klein, the research psychologist, described the problem in a 2007 Harvard Business Review article. People often hold back reservations during the planning phase, and that is exactly when raising them is cheapest. His proposed fix is a short exercise called the premortem.
What is a project premortem?
A project premortem is a structured meeting held before a project starts, or before a major phase begins. The team is told to assume the project has already failed badly. Each person then writes down the reasons why.
It is the opposite of a postmortem. A postmortem asks what went wrong after the damage is done. A premortem asks the same question while the plan can still be changed at almost no cost.
Why does imagining failure work?
There are two mechanisms, and they reinforce each other.
The first is cognitive. Klein cites a 1989 study by Deborah Mitchell, Jay Russo and Nancy Pennington on what they called prospective hindsight: imagining that an event has already happened. In his account, the technique raised people's ability to correctly identify reasons for future outcomes by 30 percent. Treating failure as a fact rather than a possibility changes the question from "could this go wrong?" to "why did it?" The second question tends to produce more specific, more honest answers.
The second mechanism is social. In a normal risk discussion, raising a concern can feel like criticizing the plan or the person who wrote it. In a premortem, finding flaws is the assignment. Klein notes that the format surfaces things people usually keep to themselves "for fear of being impolitic."
One caution is worth stating plainly. The 1989 research tested whether imagining an outcome helps people generate explanations. It did not test whether premortems improve project results. The method is best understood as a well-reasoned practice, not a guaranteed fix.
Why does early risk detection matter?
Project performance gives plenty of reason to look for better habits. The Project Management Institute (PMI) reported that the share of projects meeting their original goals and business intent fell from 72 percent in 2008 to 62 percent in 2012. In its 2017 Pulse of the Profession, PMI found that organizations wasted an average of $97 million for every $1 billion invested in projects and programs in 2016. Those are older figures, and the exact numbers shift from year to year, but the pattern is consistent: a meaningful share of project spending does not deliver what was intended.
How do you run a premortem? A five-step format
A premortem does not need special software or a long calendar block. A workable session takes about 45 minutes for a team of six to ten people.
- Time it right. Hold it once the plan is detailed enough to critique but before money, people and public commitments are locked in. Right after the charter is approved is a common moment.
- Set the scene. State it as fact: "It is one year from today. The project has failed completely. Take five minutes and write down every reason you can think of." Ask people to write silently so that senior voices do not anchor everyone else.
- Collect without debate. Go around the room and ask each person to read one reason from their list, then repeat until every item is out. No one defends the plan during this step.
- Group and rank. Cluster similar reasons, then ask the team to pick the three to five that are most likely or most damaging.
- Change the plan. For each top risk, agree on an owner, an early-warning signal and a specific change to the plan. A risk without an owner is just a worry.
A hypothetical example
The following scenario is illustrative and does not describe a real engagement.
Imagine a 40-person company replacing its billing system. In the premortem, the team writes that the project failed. The reasons that emerge: finance was never asked about invoice formats, the data migration was only tested on clean records, go-live was scheduled for quarter-end week, and the vendor had one integration engineer who might go on leave.
None of these items is exotic. Each one was visible to someone in the room. After the session, the team moves go-live two weeks, adds a migration test using the messiest customer records, and makes finance sign-off a formal gate. The plan is better, and nobody had to be the person who "negatively" criticized it.
What mistakes weaken a premortem?
- Running it too late. Once the contract is signed and the launch date is public, the team will treat findings as threats rather than information.
- Letting the most senior person speak first. Silent writing before discussion is the simplest safeguard.
- Treating it as a venting session. The output should be a ranked list with owners, not a mood.
- Skipping follow-through. A premortem whose list is never revisited is a ritual. Put the top risks on the agenda of your regular status meetings.
- Doing it once. Large projects change. Repeat the exercise at major phase gates.
Questions to ask before you schedule one
- Is the plan specific enough that people can find real flaws in it?
- Who sees risks the project manager cannot, such as finance, operations, legal or frontline staff?
- What decisions are still cheap to change?
- Who will own the follow-up?
Frequently asked questions
What is the difference between a premortem and a risk register? A risk register records and tracks risks over time. A premortem is a one-time generation exercise that feeds the register with candid, specific items.
How long does a premortem take? Most sessions fit into 30 to 60 minutes.
Who should attend? The core team plus people who will be affected by the outcome but are not on the project plan, such as a representative from operations or customer support.
Does a premortem work for Agile teams? Yes. It fits before a major release or a large body of work, where a short session can surface risks that sprint-level planning misses.
The takeaway
Plans fail for ordinary reasons that someone usually saw coming. A premortem gives those people a legitimate moment to say so. Thirty to sixty minutes of imagined failure is a small price for finding the problem in week one instead of week twenty.
Sources and references
- Gary Klein, “Performing a Project Premortem,” Harvard Business Review, September 2007 (30 percent finding, prospective hindsight, "impolitic" quotation).
- Project Management Institute, “The High Cost of Low Performance”, Pulse of the Profession, 2013 (72 percent in 2008 to 62 percent in 2012).
- Project Management Institute, Pulse of the Profession 2017 coverage, 2017 ($97 million per $1 billion wasted in 2016).
- Mitchell, D., Russo, J. E., and Pennington, N. (1989), "Back to the future: Temporal perspective in the explanation of events," Journal of Behavioral Decision Making (as cited by Klein).